Monthly Balance
In August, total consumption amounted to 3 071 GWh, divided into 2 118 GWh in the conventional segment and 953 GWh in the electricity production segment. The consumption peak occurred on 13 at 20:00 with 6 181 MWh. The system was supplied with 100% of gas from the Sines LNG terminal, where 5 ships unloaded this month, and 0% from the interconnection with Spain.