Monthly Balance
In August, total consumption amounted to 3 488 GWh, divided into 2 164 GWh in the conventional segment and 1 324 GWh in the electricity production segment. The consumption peak occurred on 7 at 19:00 with 6 038 MWh. The system was supplied with 99% of natural gas from the Sines LNG terminal, where 4 ships unloaded this month, and 2% from the interconnection with Spain.