Monthly Balance
In February, total consumption amounted to 4 609 GWh, divided into 2 775 GWh in the conventional segment and 1 833 GWh in the electricity production segment. The consumption peak occurred on 3 at 20:00 with 10 357 MWh. The system was supplied with 78% of natural gas from the Sines LNG terminal, where 4 ships unloaded this month, and 22% from the interconnection with Spain.